BatesNews Monthly Update: August 2010

For Bates alumni, parents, and friends, here is a look back at stories that represent some of the major Bates…

Thursday

June 3, 2010
5:55 pm

BatesNews Monthly Update: June 2010

For Bates alumni, parents, and friends, here is a look back at stories that represent some of the major Bates…

Friday

February 8, 2008
10:23 am

Campus construction update: Week of Feb. 4

With the official opening just weeks away, the new dining Commons passed a milestone early on Feb. 7: the arrival of its first truckload of food.

Tuesday

January 22, 2008
3:44 pm

Campus construction update: Week of Jan. 21

In recent weeks we’ve learned what Dining Services director Christine Schwartz likes about the new dining Commons. Now it’s the turn of Paul Farnsworth, Bates’ project manager for the building. A mechanical engineer, Farnsworth especially appreciates the ventilation scheme. There’s no building-wide air conditioning per se. Instead, it’s essentially a natural system, he explained: the high-peaked main dining hall and an adjacent airshaft will create a chimney effect to pull fresh air in through windows that can actually be opened — an unusual feature these days in large new buildings.

Tuesday

January 8, 2008
2:13 pm

Campus construction update: Week of Jan. 7

A student serving on a food advisory committee once told Christine Schwartz, Dining Services’ director, that anticipating a meal at the current Memorial Commons is like getting psyched up for battle. “You pretty much have to fight your way through Commons now” because of the way the space is arranged, Schwartz said. New arrivals at mealtime, still burdened with coats and backpacks, immediately find themselves in a confusion of food stations and fellow diners pressing in all directions. All that will change when the new Commons opens in February.

Thursday

October 25, 2007
10:48 am

Campus construction update: Week of Oct. 22

The project isn’t inspiring like Alumni Walk, magnificent like the new dining Commons or heartwarming like the new student housing. But a new parking lot behind Merrill Gymnasium that should open around Thanksgiving will come in handy, easing the squeeze that Bates motorists have felt the past six months.

Thursday

October 25, 2007
9:45 am

Campus construction update: Week of Nov. 5

The new dining Commons should be open for business when students return from break on Feb. 25, project manager Paul Farnsworth reported. And it’s hoped that construction work will be complete about a month prior to the opening.

Friday

October 12, 2007
12:41 pm

Campus construction update: Week of Oct. 8

Oct. 8 was a red-letter day at 280 College St., as the outdoor gas grill at the new student residence was fired up for the first time. Residence coordinators Jenn Linton ’08 and Matt Lopez ’08 hosted an inaugural cookout that had been delayed a couple weeks while shipping damage to the grill was fixed.

Friday

September 28, 2007
2:11 pm

Campus construction update: Week of Sept. 24

An afternoon thunderstorm on Sept. 27 occasioned an Alumni Walk first: emergency vehicles entering in response to a campus alarm. Although there was no fire, lightning caused a power surge in the fire detection system, frying a computer chip and setting off an alarm in Hathorn Hall.

Friday

September 14, 2007
3:58 pm

Campus construction update: Week of Sept. 10

Paul Farnsworth, manager of the new dining Commons and Alumni Walk projects, reported that 140,000 flower bulbs were shipped our way from California on Sept. 11. The bulbs are scillas, which bloom around the same time as crocuses.