Stories about "housing"
A technician for Exposé Signs & Graphics has just finished mounting a sign for the College Store on a front canopy at 65 Campus Ave.  (Doug Hubley/Bates College)
Campus Construction Update: Aug. 26, 2016

Friday, August 26, 2016 11:42 am

Produced in collaboration with Museum L-A, wall art in Bates College's new student residences honors Lewiston history and creativity.

The exterior wall coverings were in place on the front of Bates' new boathouse by late July 2016. (Doug Hubley/Bates College)
Campus Construction Update: Aug. 12, 2016

Wednesday, August 10, 2016 4:04 pm

The four Bates College construction projects that we've been following for months are all coming to fruition in the next few weeks.

55 Campus Ave. on Aug. 5, 2016. (Doug Hubley/Bates College)
Campus Construction Update: Aug. 5, 2016

Friday, August 5, 2016 11:14 am

July has been a thrill ride in the progress of Bates College's new student residences, but a recent development gave us a particular tingle.

A pipefitter for Johnson & Jordan works in the basement of Smith Hall. (Doug Hubley/Bates College)
Campus Construction Update: July 15, 2016

Wednesday, July 13, 2016 3:00 pm

Campus Construction Update was impressed to see incisions that had been made in the back wall of Wentworth Adams Hall in late June.

Facing north in the lobby of 55 Campus Ave. on June 30, 2016. (Doug Hubley/Bates College)
Campus Construction Update: July 8, 2016

Friday, July 8, 2016 10:32 am

The construction work on Bates College's new residences at 55 and 65 Campus Ave. is winding down.

160608_CCU_Boathouse_Medium_View_2228-dlh
Campus Construction Update: June 10, 2016

Friday, June 10, 2016 8:44 am

The new Bates College boathouse now has a roof and some walls, and two dorm improvement projects will shift into high gear after Reunion.

New plantings at 65 Campus Ave. on May 31, 2016. Note the ground cover at left — some 6,000 barren strawberry and sedge plants covering a storm runoff site. (Doug Hubley/Bates College)
Campus Construction Update: June 3, 2016

Friday, June 3, 2016 10:11 am

Site work is dramatically transforming the 65 Campus Ave. residence at Bates College.

The construction fence was on its way out and Gendron & Gendron was doing site work at 65 Campus on April 15, 2016. (Doug Hubley/Bates College)
Campus Construction Update: April 29, 2016

Friday, April 29, 2016 10:35 am

All right, New Jersey didn't ask for its barriers back. But those concrete blocks and attached fence are nevertheless leaving the Campus Avenue work sites.

Smith Hall, viewed from the 60-foot Campus Construction Update stepladder. (Doug Hubley/Bates College)
Campus Construction Update: April 14, 2016

Thursday, April 14, 2016 10:58 am

Short Term will see the start of significant renovations to Smith and Wentworth Adams halls. The biggest news involves Smith, where quads will become doubles.

The view from a third-floor technology room at 55 Campus Ave. on March 22, 2016. (Doug Hubley/Bates College)
Campus Construction Update: March 25, 2016

Friday, March 25, 2016 1:09 pm

While a timetable is yet to be finalized, the beginning of April will likely see the start of site work at the new Campus Avenue Project residences.