October 25, 2007 9:45 am

Campus construction update: Week of Nov. 5

The new dining Commons should be open for business when students return from break on Feb. 25, project manager Paul Farnsworth reported. And it’s hoped that construction work will be complete about a month prior to the opening.

Friday

October 12, 2007 12:41 pm

Campus construction update: Week of Oct. 8

Oct. 8 was a red-letter day at 280 College St., as the outdoor gas grill at the new student residence was fired up for the first time. Residence coordinators Jenn Linton ’08 and Matt Lopez ’08 hosted an inaugural cookout that had been delayed a couple weeks while shipping damage to the grill was fixed.

Friday

August 31, 2007 8:39 am

Campus construction update: Week of Aug. 27

On Friday, Aug. 31, construction crews rushed to get much of Alumni Walk ready for traffic as students returned in force. The short-term objective is to open the walk from College Street as far east as Pettengill Hall. The entire walk won’t be finished for weeks, and even in the section soon to open, landscaping chores, the placement of benches and lights, and similar work will continue.

Friday

April 6, 2007 12:03 pm

Campus construction update: Week of April 9

Between the mud, the plastic wrap and the concrete, the colors of construction work are predominantly drab. But the rare “colorful” colors, as major projects building at Bates this year have shown, can be surprisingly bold.

Tuesday

January 9, 2007 11:57 am

Campus Construction Updates: Week of Jan. 8

Campus Construction Updates: Week of Jan. 8

About nine months remain before students move into the new student housing, adjacent to Rand Hall.