The number of on-site workers and the range of trades represented made May the busiest month for the construction of the new student housing. On May 3, 128 non-Bates workers in 13 categories put in a grand total of 1,071 hours. This May 3 breakdown shows, in descending order of total hours per trade, the number of workers in each trade.
| Trade |
Crew Size |
Total Hours |
| Drywallers |
32 |
272 |
| General Contractors |
21 |
189 |
| Masons |
22 |
176 |
| Floor Finishers |
9 |
72 |
| Mechanic Technicians |
9 |
72 |
| Electricians |
7 |
56 |
| Framers |
5 |
50 |
| Roofers |
6 |
48 |
| Painters |
5 |
40 |
| Ironworkers |
4 |
32 |
| Fire Protection Technicians |
3 |
30 |
| Waterproofers |
3 |
18 |
| Elevator Technicians |
2 |
16 |
Source: Pam Wichroski, student housing project manager, Physical Plant